Hi Civil Engineers , Welcome In today’s article you are going to learn about the different methods of Estimation for building, Long Wall — Short Wall Method and Center Line Method.

You will learn the above methods of Estimation of the building in Complete details.

So, Let’s Start.

Building Estimation of Long Wall Short Wall And Center Line Method

Estimation of Building

Estimation is an art to calculate the Quantities & cost of the different materials used in the building before its Construction.

Building Estimate is of 2 types one is known as Rough Cost Estimate.

This estimate will not describe the exact cost of building, but it can give you the approximate cost value of the building that will assist sufficiently in the Managing money for building.

Rough Cost Estimate is conducted in the different ways for different kind of the buildings.

An estimate is done for any project before commencing about its fruitfulness & cost that will be expended on it.

Rough Cost Estimate is conducted in the different manners for different types of projects.

Another famous method of the building estimation is Detailed Cost Estimate.

In this method of the estimation of the building, each item of the project is determined & multiplied by its unit of the Rate to acquire the cost.

Every types of cost is involved in the Detailed Estimate. Therefore, it is considered the better estimation method.

Detailed Estimate is conducted to get the approval of the Technical Sanction of the related project.

Technical Terms used in the Building Estimation.

Different Technical terms are used for the making building estimate. Some important technical terms are described below.

1 . Plinth Area.

Plinth Area is the constructed area over the floor surface. It also includes the area of the veranda & other passages that have a roof over them.

Plinth Area is measured up to outer edges of walls.

2 . Floor Area.

Floor Area includes the internal area of all the rooms. Rooms include kitchen, bathroom, & stair room. It does not include area encapsulated by walls.

3 . Carpet Area.

Carpet Area refers to the area of the residential rooms. It does not include areas of the kitchen, bathroom, & stair room.

4 . Market Rate.

Market Rate is the per unit rate of the different objects available in the market. It also Includes conveyance charges, wastage charges, & taxes imposed over objects.

Learn More

  1. Building Estimation By Centre Line Method

  2. What is Gravity Dam?

5 . Schedule of Rates.

Civil Engineering departments prepare rates according to the market rates for the payments that are known as Schedule of Rates.

It includes rates of the cement, sand, gravel, & steel bars, etc. However, It also shows rates of labor or material as well.

Rates of labor are known as Labor Rates. Rates of labor along with material are known as Composite Rates & shortly known as C.S.R.

Schedule of Rates is regularly issued observing the rates fluctuation in market.

It is issued at the start of each year that will be practicable for at least three months. Which is known as Market Rates Schedule that is uploaded on the Internet and shortly known as MRS.

6 . Premium.

Rates are subjected to increase even after the issuance of the Schedule of Rates that is why additional rates are decided during the agreement with the contractor.

That is known as Premium.

7 . Rebate.

Rebate is also subjected to decrease even after issuance of the Schedule of Rates.

Decreased rates are decided during agreement with the contractor that is known as Rebate.

8 . Contingencies.

Estimates will incorporate some items that are not listed with the particular headings.

three to 5%, of the overall budget, is reserved for encapsulating the cost of these items that are known as Contingencies Charges.

9 . Petty Items.

There are certain items which cannot be determined exactly during the preparation of estimates.

These Items are known as Petty Items.

10 . Bill of Quantity.

Bill of Quantity is the statement of the items of work. This statement will include item names along with the description of work and quantity of work.

However, empty cells are left for related rates and amounts that is submitted by the contractor as B.O.Q.

This statement will be known as Abstract of Cost once rates and amounts are filled in.

11 . Capital Cost.

Capital Cost is the overall cost paid out over the project.

It includes construction cost, survey cost, design and supervision cost, water supply cost, sanitary cost, electrification cost, classification cost, and plot price cost, etc.

12 . Prime Cost.

The amount is reserved during the preparation of the estimates that will be expended over the certain things with the approval of owner or project manager or site engineer.

It may include pay out over fittings of doors and windows, water supply, sanitary, and electrics fittings, etc.

This amount is known as Prime Cost.

Learn More

  1. What is the Construction Risk Management

  2. What Is Difference Between P.P.C And O.P.C Cement

13 . Provisional Sum.

An amount is reserved during the preparation of the estimates expended over items that are not determined.

This amount is known as Provisional Sum such as the cost of installation of telephone, or gas, or Internet and installation of air conditioners, or lifts, etc.

14 . Work Charge Establishment.

Staff is enlisted during the construction of the project on the temporary basis that is known as Work Charge Establishment.

This staff includes secretaries, mates and security guards, etc.

They are enlisted for a short time. 1.5 to 2% of the overall cost is reserved for payment of their salaries or wedges.

15 . T. and P. Charges.

One to 1.5% of the overall cost is reserved for tools and giants during the preparation of the estimates which is known as T. and P. Charges.

Here, T stands for Tools and P. stands for Plants.

Methods of Estimation of Building.

Estimation of the building can be done by different methods as follow.

1. Long Wall – Short Wall Method.

2. Center Line Method.3. Crossing Method.

So, Let’s discuss the methods of Estimation of building.

1 . Long wall – Short wall Method.

In Long wall – Short wall method of the estimation, the external wall along the length of the room is intended to be Long wall while the wall perpendicular to the long wall is stated to be a Short wall.

To get the length of the long wall or short wall, calculate first the centerline lengths of the particular wall.

Then the length of the long wall, (out 2 out) may be measured after adding half breadth at each end to its center-line length.

Thus, the length of the short wall measured into in and may be found by deducting half breadth from its centerline length at each end.

The length of the short wall usually increases from the earthwork to brickwork in superstructure while the long wall decreases.

These lengths are then multiplied by depth & breadth to get quantities.

In short wall & long wall method, the wall along the length of the room is considered to be a long wall, while the wall perpendicular to a long wall is known to be a short wall.

2 . Center Line Method.

In Center Line method of the estimation, measurements of the wall are taken up 2 center. Internal measurements are generally taken.

The thickness of the half wall from one side & thickness of half wall from another side in internal measurements are added in order to determine the length of Center Line of the room walls.

If all of the steps are symmetrical in cross-section of the wall, then the total length of Center Line will be uniform for all items of the wall.

If these steps are not symmetrical, then the length will be determined separately for each step.

Despite, if the design of walls is same throughout in building then it is quite easy to find the length of the Center Line.

Center Line method is employed easily in circular & polygonal shaped buildings.

Despite, this method is also suitable to use in the small buildings with few rooms.

3 . Crossing Method.

If the thickness of external walls is of the same thickness in the overall building & the internal walls are also of the same thickness, but they both are of the different thickness from each other.

Then this method is used for Estimating.

In such cases, the center line method is used for external walls, and long wall – short wall method is used for the internal walls.


Other Post 

  1. How To Calculate the Estimate Of U Shape Wall

  2. What Is The Working Principle of Base Insulation System


 

We hope this Article is helpful for Civil Engineers and QS . If You think it is useful and Informative kindly Get Benefits And Share With Others.

Thank You.

Lets Come TO Join Us Our Official Facebook Page.

( Civil Engineering Technology )

Civil Engneering Technology

Civil Engineering Technology is Educational and Training Blog for Engineering Students. Our Mission is to Educate And Keep People Informed By Creating a Trusted Source Of Knowledge Everything Related To Civil Engineering. Please Give Us Your Valuable Feedback And Suggestions. We Will Appreciate Your Opinions And Will Use It To Evaluate Changes And Make Improvements On Our Site. Thank You